Time-on-Tools and Minimum Required Installation

Labor productivity IS NOT the biggest problem with field productivity. Under similar conditions the variation in how fast two crafts people actually “turn wrenches” is about 2X but there are far bigger problems to tackle. Focus on these three areas.

D. Brown Management Profile Picture
Share

 

Field Productivity: Labor Productivity IS NOT The Biggest Problem With Project Productivity

 

  1. Maximize Time-on-Tools (ToT): Ensure that crafts people spend most of their day working with their tools actually installing things.  Different studies place the industry average between 50-65%.  Leverage the 6 Pillars of Productivity and ABC Daily Planning.  
  2. Minimum Required Installation (MRI): Don’t take critical shortcuts but don’t over-build the project.  In the field we would call it “Gold Plating.” Effective installation details, craft training and good field supervision practices will ensure that you get the right level of quality. 
  3. Minimize Rework: The only greater waste than installing more than what is required is doing it twice.

General Contractors and Project Owners can do a lot to set the conditions for success with their labor-intensive subcontractors. 


4 Elements of an Effective Task

Site Logistics Management


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Impacted Productivity - Stacking of Trades and Installation Efficiency
Each craftsperson needs about 200 usable square feet for a productive installation. This assumption is included in production units used to estimate and budget projects. Having less than that can impact productivity up to 50%.
Changes - Early Identification is Always Better
Early identification of changes and conflicts is the first key to success. The capability to identify changes and conflicts early in the process is a combination of organizational structure, systems, management, training, and coaching.
Early Identification as a Trainable Skill
The ability to identify potential changes early is a skill that can be tested, trained, and managed just like a craft skill.