Pull Planning and the 4 Most Powerful Words

“What do you need?” are the four most powerful words for improving field productivity on construction projects.

D. Brown Management Profile Picture
Share

This lesson can be best illustrated by superintendents from two different general contractors who were building identical projects in different parts of town in 1990. 

Field Productivity: Lean Principle - Pulling vs Pushing. The 4 Most Powerful Words for Improving Productivity.



One superintendent was very experienced and directed all of the subcontractors on what to do. The other superintendent had almost no experience and would get all the subcontractors together in his trailer looking at the project schedule together on the wall.  

He would then pull out his notepad and start asking each trade foreman “What do you need?”  He wrote it all down and worked hard to get everyone what was needed so everyone could complete their work effectively. 

The project with the less experienced superintendent finished 3 months earlier with less change orders!

In 1990, the term lean was only starting to enter people’s vocabulary based on a paper written by John Krafcik in 1988. It wasn’t until 1997 that the Lean Construction Institute was founded and their flagship tool called the Last Planner System was introduced. 

Lean tools and the Last Planner System really just codify what the best superintendents and managers have been doing - creating a scalable system.  


Learn More (Pull Planning)

What Is Lean and Lean Construction?



 


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Lean Principle - 3 Enemies of Lean
Profitable growth comes from operating within a target capacity and capability range - and continually increasing those ranges. Operating with consistent overload, consistent under capacity, or with consistently high variability is not sustainable.
Field Productivity - The Improvement Pyramid
An improvement of a few minutes per day to actual installation time compounded monthly is worth about $800K per year for a $25M contractor. What is it worth to you? Improvements to field productivity can be viewed as 4 major stages of a pyramid.
Creating The "Perfect Field Day"
Contractors build things and that comes down to the men and women in the field. They are the ones adding the value to the raw materials and that is ultimately what the customer is paying for.