Higher Scores Aren’t Always Better: Percent Planned Complete (PPC) Example

Construction is full of competitive personalities - more is always better. This is not always the case, and you must be careful when setting targets that your goals don't have unintended consequences. Percent Planned Complete (PPC) is a perfect example.

Joseph Irby Profile Picture
Share

 

 

Percent Planned Complete (PPC) is a critical measure of a weekly work plan or SIP (Short-Interval Plan). 

David MacNeel from On Point Lean describes that higher scores aren't always better in this interview with Felipe Engineer-Manriquez on the EBFC (Easier, Better, for Construction) Show (4 minutes starting at 0:20:00)

 

 

54% was the average amount of weekly tasks that got completed as planned when Greg Howell and Glenn Ballard first studied the problem in the late 90s. 

Low to Mid 70s: Likely on-track with schedule and productivity (Two Key Results for Project Planning)

High 70s to High 80s: Likely ahead of schedule and productivity targets. 

High 80s to Low 90s: Great team and conditions.

Mid to High 90s: Likely gaming the system - sandbagging or misreporting. 


 

An important part of your scorekeeping process is setting appropriate targets with tolerances and clear management escalations if there are large variances, or they are trending in the wrong direction for too long. 

 



Related Training

Lean Principle - Value Stream
A contractor’s value stream is every step required to take raw materials and information then deliver a completed project to the waiting hands of a customer. Deep understanding of this value stream is the foundation for major productivity improvements.
Percent Planned Complete (PPC) - Calculation Example
Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.” This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement.
Lean Principle - Stop Work (Until Problems Are Corrected)
All construction projects will run into some degree of problems. It is how the project team chooses to manage these problems that ultimately determines the outcome of the project.