Impacted Productivity - Disrupted Workflow (No Schedule "Flow")

One of the biggest impacts to productivity in construction is when tasks can not be completed as planned.

D. Brown Management Profile Picture
Share
Field Productivity: Impacts - Disrupted Workflow.

 

  • The project schedule for other trades and tasks must be adjusted often, causing overall project delays, increased “Bad Stress” on the project team, or both.  
  • The actual task itself costs more than budgeted by contractor. At a minimum, the interruption will cost additional mobilization to and from the work area. Remember that about 19% of the labor hours in a typical construction day are spent figuring out what to do, gathering materials, and site movement. When a task is interrupted, you often have to repeat some or all of these non-installation tasks.  

When this happens frequently, it starts to impact every aspect of the contractor’s scoreboard in a negative way starting with customer satisfaction.

Weekly feedback and learning systems are a core element of the Last Planner System because their research showed that tasks not being completed as planned were the single biggest source of poor project performance.  

 

Focusing on planning Effective Tasks, the 6 Pillars of Productivity, and ABC Daily Planning will keep your project on-track.  

 


Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Labor Productivity
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

The Truth About Leading Change
Few things are more important for a growing contractor than leadership and management being effective in how they make decisions about change, communicate those decisions, and help their teams navigate the process.
Two Planning Dimensions
Some of the impacts you see on a project are not as clear as a design change, conflict, or obviously changed condition. Some impacts, such as poor project sequencing or congested work areas are hard to notice if you don’t have good tracking systems.
Changes - Impacts Beyond the Direct Costs
Contractors don't typically see the full negative impact of changes and, therefore, don’t put the right level of resources into their management.