Percent Planned Complete (PPC) - Calculation Example

Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.”

D. Brown Management Profile Picture
Share
Field Productivity: Percent Planned Complete (PPC). Do or do not. There is no try.

This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement. Measurement of PPC is rigorous:

  • Partially complete tasks DO NOT count.
  • Extra tasks (not planned) DO NOT count.
  • Reasons why DO NOT matter except for the weekly learning aspect. 

Imagine designing a field supervisor coaching program with PPC at the center.  

For 12 weeks, an experienced coach would work hands-on with a Foreman starting with a review of their PPC from the prior week and then developing the next week’s Short-Interval-Plan (SIP), focusing on:  

This coaching will improve the Foreman’s capability to execute their key responsibilities and achieve their key results.  


Field Productivity Workshop



Related Training
More from D. Brown Management
Learning, Doing and Teaching
Growth in life, career, and business is about a continual cycle of learning, doing, and teaching.
Ownership Transition - Key Buyer Risks
While different, buyers of a construction business have just as many risks as sellers. Deeply understanding the risks for both parties is a great start to creating the foundation of a deal.
Delivering Advanced Preconstruction Services
Delivering Advanced Preconstruction Services is the rigorous process of ensuring budgets are met along with maintaining features critical to the project owner / users.