Percent Planned Complete (PPC) - Calculation Example

Yoda would be the perfect coach for managing schedules on projects: “Do or do not. There is no try.”

D. Brown Management Profile Picture
Share
Field Productivity: Percent Planned Complete (PPC). Do or do not. There is no try.

This is the heart of Percent Planned Complete (PPC) and the weekly cycle of continuous production improvement. Measurement of PPC is rigorous:

  • Partially complete tasks DO NOT count.
  • Extra tasks (not planned) DO NOT count.
  • Reasons why DO NOT matter except for the weekly learning aspect. 

Imagine designing a field supervisor coaching program with PPC at the center.  

For 12 weeks, an experienced coach would work hands-on with a Foreman starting with a review of their PPC from the prior week and then developing the next week’s Short-Interval-Plan (SIP), focusing on:  

This coaching will improve the Foreman’s capability to execute their key responsibilities and achieve their key results.  


Field Productivity Workshop


Percent Planned Complete (PPC) - Calculation Example
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Related Training
Percent Planned Complete (PPC) - Calculation Example
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Impacted Productivity - Dilution of Management
Dilution of management will compound an already impacted construction project. It is important for teams to realize the full costs of impacts as they start to occur.
Continuous Improvement: Plan, Do, Check, and Act (PDCA)
Improving productivity in construction is exceptionally challenging. It must be embraced as a journey and not a destination. It must be made into a game so that people clearly see what winning looks like and fall in love with the process.
Two Planning Dimensions
Some of the impacts you see on a project are not as clear as a design change, conflict, or obviously changed condition. Some impacts, such as poor project sequencing or congested work areas are hard to notice if you don’t have good tracking systems.