Production Tracking - Troubleshooting Problems

Implementing production tracking without a program to ensure effective troubleshooting of the problems will be minimally effective.

D. Brown Management Profile Picture
Share
Field Productivity: Troubleshooting Problems when Production Tracking.

Look at this in two major stages:

  1. Simply learning to see the problems using tools like tracking weekly Percent Planned Complete (PPC) and daily Production Tracking.  
  2. Learning how to troubleshoot the problems using techniques like 5 Why and then test improvements ultimately resulting in new standards.  

EXAMPLE:  

  • What Happened?  Branch raceway production has been 30% lower than planned
  • Why?  Framing installation fragmented.
  • Why did we start?  Had to meet the project schedule. 
  • Why couldn’t we delay our start?  Key customer and they sent threat of backcharge.
  • Why couldn’t we compress our install window?  Not enough manpower.
  • Why didn’t we use prefab to compress install?  Did not plan project thoroughly.
  • Why?  Project started with 5 days notice.
  • Why didn’t we make the time to plan; even if on the weekend or overtime?  Project team does not truly see the value in planning or prefab.  
  • Why?  Zero time invested in training or coaching around project planning.
  • Why?  Leadership team is focusing nearly 100% of their time opening new branch office.
  • Why?  It is an opportunity to grow revenue and profits while diversifying the company for the next economic downturn.

What are the “WHY’s” behind your production misses last week?    

What is your improvement plan?  

Improving Labor Productivity Workshop


Production Tracking - Troubleshooting Problems
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Production Tracking - Troubleshooting Problems
Field labor is the often the biggest variable on a construction project - making it the biggest risk and opportunity....

Owner Occupied Real Estate for Contractors - Lease or Buy?
There isn't a simple answer to this question. Much of the advice you will get has bias attached. Start your decision making process by building your own models and making general assumptions while looking into the future. Use this Excel model to start.
Cash Flow Tip 3 - Contractual Details Matter
The reason we are called contractors is because we work off of a contract that defines the scope and terms of what we build. How we negotiate and manage the contract determines cash flow.
Project Delivery - CM Agency or Multi-Prime
Project Owners can minimize the markups for overhead and profit by contracting directly with the specialty contractors and hiring a Construction Management (CM) firm to work as their agent. This project delivery method is called CM Agency or Multi-Prime.